Description of Project:
Award a best value contract to remove and replace ~7,200’ of Blue Hill Drive and adjoining cul-de-sac roads, water service feeder lines, and water meters as designed in FY2021 by KPFF. Construction will be managed by a professional Construction Manager to ensure selected contractor delivers goods and services as specified in design documents.
Basis for Project:
As noted in the 10-Year Roads and Water Plan report prepared by KPFF Engineers, the most significant road wear exists on the front/back gate entrance roads and Rampart. Additionally, a significant cost saving opportunity exists in partnering with Weyerhaeuser when they replace their road that runs parallel to Blues Hill Drive in 2022.
Value to Membership:
High reliability of water distribution, water quality, protection of road from under road culvert that will handle the increased water flow from the Weyerhaeuser road change adjacent to CCA property.
If utility providers participate during the design process, our road construction will incorporate their utility upgrades of their service lines at their expense. We will have provided them the opportunity to save money and upgrade their utilities to the members but there is no guarantee.
Preliminary Cost/Schedule:
The completed 10-Year Plan reflects a Total Estimated Construction Cost of $1,014,208 which includes a 10% construction contingency held by CCA for this specific construction project. Schedule will be generated by the contractors as part of their bids.
The images below reflect the year in which Project 1B will be completed and the location of the work.